Construction on Fuengirola’s new market. Credit Viva Fuengirola FB
Fuengirola’s long-awaited new Mercacentro market is now not expected to be completed until the first half of 2027, almost two years after its original opening date.
The €14 million redevelopment has suffered repeated setbacks, leaving traders and residents waiting for a replacement building that was supposed to be ready in July 2025.
Why has the new Mercacentro taken so long?
Construction began on January 22, 2024, with an original timetable of just 18 months. However, unexpected structural problems were discovered after the old Fuengirola market closed for redevelopment. Engineers found that the existing basement floor slab was not as expected and could not be relied upon to support the proposed new building.
Work was temporarily halted while the project was redesigned, with construction restarting in April 2025. The budget also increased from €12.98 million to approximately €14 million. A revised completion date of October 1, 2026, was subsequently agreed, but that deadline has also passed.
Fuengirola Town Hall has acknowledged further problems involving the building structure, supplies of construction materials and the companies forming the construction consortium. A technical modification, signed off for processing in October, is intended to improve materials and installations without increasing the budget. However, it requires another revised construction schedule. The council now expects the work to finish during the first six months of 2027.
What will the new market offer?
The redesigned Mercacentro will cover more than 11,000 square metres across several floors. Its ground floor will house 39 traditional market stalls, while the first floor is planned for restaurants, gastro bars and a business incubator. A public terrace will occupy the top floor, with underground parking and dedicated loading facilities also included. Much of the structure uses cross-laminated timber, a construction method intended to improve energy efficiency.
What about Fuengirola’s bus station?
Another long-discussed town centre project concerns the ageing bus terminal in Calle Alfonso XIII. Fuengirola’s bus station upgrade plans have also been under discussion for some time.
Fuengirola Town Hall and the Junta de Andalucia are working towards commissioning a project to improve the existing facility, with better passenger access, shaded waiting areas, improved safety and traffic circulation. The council’s announcement on the bus station improvements provides further details.
The terminal handles more than 200 buses daily, rising above 300 during busy periods, and serves around two million passenger journeys annually.
A completely new location is also being investigated, although no alternative site or construction date has been confirmed.
For now, passengers should expect improvements to the existing terminal rather than a new bus station. With the market already years behind schedule, residents will be hoping the next major Fuengirola infrastructure project progresses more smoothly.